Laboratory HVAC Retrofit Projected to Cut Utility Costs by 45% and Reduce EUI by 60%

Modern Maryland commercial property featuring a glass stairwell, trees in front, and blue sky in the background.
45%
PROJECTED UTILITY COST SAVINGS
$517K
GRANTS + UTILITY INCENTIVES
60%
EUI REDUCTION

Overview

Nearly $419,000 in annual utility costs made it clear Fisher Lane needed more than a one-for-one equipment replacement. The Rockville laboratory and office building was operating with aging mechanical systems, high ventilation demands, and significant energy waste.

Laboratory buildings typically use more energy than offices because they must condition large volumes of outside air. At Fisher Lane, oversized equipment, 24/7 ventilation, and exhaust air leaving the building without heat recovery added to the load.

The building also faced a larger capital decision. Its chillers and boilers were nearing the end of their useful life, and its Energy Use Intensity (EUI) was 439 kBtu per square foot per year, well above Montgomery County’s BEPS target of 212.

Spectrum evaluated the mechanical systems and the project economics together, identifying opportunities to right-size equipment, recover wasted energy, improve controls, and pursue available funding.

By looking at system performance and funding together, Spectrum helped turn a necessary equipment replacement into a stronger capital investment.


Challenge

High Energy Costs Were Only Part of the Problem

Fisher Lane was operating at more than 14 air changes per hour, 24 hours a day while exhausting approximately 25k CFM of conditioned air without heat recovery.

The central plant was also oversized and complex. Two aging 270-ton chillers were serving a calculated cooling load of approximately 180 tons. The system included end-of-life steam boilers, steam humidification, and as many as 17 pumps in a primary-secondary configuration.

Controls added to energy waste. Pumps could run while the chiller was off, and ventilation schedules did not reflect actual occupancy.

A one-for-one equipment replacement would have carried many of those inefficiencies forward. The project team needed to determine the actual loads, simplify the system, and identify which improvements could qualify for funding.

Solution

Right-Size Equipment, Recover Energy, and Improve Control

Spectrum began with a feasibility study to determine the building’s actual cooling, ventilation, and operating requirements.

The analysis showed the existing equipment was oversized and unnecessarily complex. The project replaced two 270-ton chillers with two 150-ton air-cooled scroll chillers and converted the pumping system from primary-secondary to variable primary operation. The new configuration reduced the chilled-water pumps from as many as 17 to two.

Aging steam boilers were replaced, humidification moved off the steam loop, and heat recovery was added to three existing air-handling units. A new building automation system coordinated equipment operation and adjusted ventilation around occupancy.

Air changes were reduced from 14 to 11 per hour while preserving the capacity needed for future laboratory tenants.

Make Funding Part of the Project Plan

Spectrum evaluated funding opportunities alongside the engineering work, before equipment selections were final. The team developed energy and cost models, evaluated applicable tax programs, identified eligible utility and grant opportunities, and managed the documentation required for applications.

Grants and utility incentives reduced the project cost by $517,000. The financial analysis also identified potential tax benefits through equipment expensing and bonus depreciation.


Results

Funding Covered 21% of the Initial Project Cost

Spectrum helped secure $217,214 in utility rebates and a $300,000 Maryland Energy Administration (MEA) grant reducing the $2.48 million project cost to approximately $1.97 million.

 

Funding breakdown for the Fisher Lane laboratory HVAC retrofit showing $217,214 in utility rebates and a $300,000 Maryland Energy Administration grant.

 

Tax Benefits Further Improved Project Economics

The financial analysis identified an additional $917,600 in estimated tax benefits from expensing eligible equipment and bonus depreciation. Combined with the grants and incentives, those estimates reduced the effective cost to approximately $1.05 million.

With $190,000 in projected annual utility savings, simple payback improved from 10.4 years to 5.5 years.

 

Fisher Lane project cost reduction showing grants, incentives, estimated tax benefits, and projected simple payback improving to 5.5 years.

 

Projected Annual Utility Costs Fell 45%

The retrofit is projected to save 833,055 kWh of electricity and 27,590 therms of natural gas annually reducing utility costs by 45%.

  • 50% less electricity use
  • 32% less natural gas use

 

EUI Fell 60%, Below the BEPS Target

Fisher Lane’s EUI fell 60%, from 439 to 175 kBtu/SF-yr, bringing the building below Montgomery County’s BEPS target of 212 kBtu/SF-yr.

The project is also expected to reduce annual emissions by 384.7 metric tons of CO2e.

Fisher Lane Energy Use Intensity before and after the retrofit, showing a reduction from 439 to 175 kBtu per square foot per year compared with the Montgomery County BEPS target of 212.

 

Details:

Property Management 
Minkoff 

Building Type 
Laboratory and office building 

Location 
Rockville, Maryland 

Project Partner 
Havtech 

Key Upgrades 
Chillers, condensing hot-water boilers, electric humidification, heat recovery, variable primary pumping, and new building controls 

Key Results
$517,000 funding secured

$190,000 project annual utility savings

60% EUI reduction

BEPS Target Achieved

*Tax benefits vary by owner and project. Consult a qualified tax advisor. 

Conclusion

A Better Capital Project Starts with Performance and Funding Analysis

Fisher Lane needed more than a one-for-one equipment replacement. By evaluateing system loads, energy waste, available funding and project economics together, Spectrum helped turn a necessary HVAC upgrade into a stronger capital investment.. 

The retrofit cut projected annual utility costs by 45%, brought the building below Montgomery County’s BEPS target, and secured $517,214 in grants and incentives. Estimated tax benefits further improved projected payback to 5.5 years. 

For building owners planning major HVAC upgrades, evaluating performance and funding together can lead to better technical and financial decisions.

Two men sitting and talking in an office with data charts displayed on a screen behind them.

Want similar results?

Spectrum Energy can help you lower costs, improve comfort, and meet local regulations—without draining your capital budget.

Talk to a Building Expert